![]() |
|
This paper covers all aspects of the Facility Control System (FCS) at the PREPA 2OMW Battery Plant, including the control philosophy developed and implemented for this application. The FCS consists of distributed control processing units, fiber optic data highway, workstations and a cell voltage and temperature monitoring system. It provides interface between the battery system and the power conditioning system (PCS) microcontroller, in order to integrate the Battery Plant operation to the power system grid. 1.0 INTRODUCTION The PREPA Battery Plant at Sabana Llana, Puerto Rico consist of the following three major components: · Two 10 MW lead acid battery strings, 3000 cells each · Two 10 MVA Power Conditioning Systems (PCS-converters) One Facility Control System (FCS) Figure 1 shows a single line diagram of the facility. The BESS Facility Control System (FCS) is based on a commercially
available Distributed Control System (DCS) manufactured by MAX Control
Systems, Inc. The control system concept for the BESS is as shown on Figure 2. The figure illustrates the interface between the plant's components and the control system. In order to realize this concept, the FCS at the Battery Plant consists of four basic components: · Fiber Optics Data Highway · Distributed Processing Units · Workstations · Cell voltage and temperature monitoring 2.1 Fiber Optics Data Highway The data highway consist of a token passing bus in a physical loop
configuration. This bus is made of a fully redundant pair of 200 micron
fiber optical cables which makes communication possible between work
stations at the control room and the Distributed Processing Units at
the FCS cabinets. 2.2 Distributed Processing Units The DPU is a data highway resident, self contained control unit that
plugs into an input/output rack. The DPU has an integral high speed
input/output processor and a dedicated data highway processor. The DPU
scans and processes information for use in reports, logs, calculations
and graphics by other FCS devices. Each DPU can support one to one backup
to provide maximum reliability. 2.3 Workstations The workstation is the operational man-system interface. Each workstation
consist of up to three PC processors, each processor having its own
duty but working together to provide the operator/engineer with valuable
information. These processors are connected together on each workstations
via an industrial standard SCSI interface. 2.3.1 Graphic Processor This is the operator's interface with the plant process. This processor
runs with Microsoft Windows Operating System and a graphic screen builder.
Among its functions is to: - Monitor and display process information from DPU'S. - Manipulation of process. - Display trending that has been collected. - Run pre-defined reports. 2.3.2 Application Processor This processor runs under UNIX Multi-user operating system and a commercial
relational database manager. Its functions are: - Build control blocks, data blocks and EXCEL (Extended Control Engineering Language) code for customized control. - Install control configuration into RTP's and DPU'S. - Access and query all system data. 2.3.3 Real Time Processor This is a highway resident processor which represents the interface
between the DPU's and the workstations. It collects and stores current
analog or discrete trend points of information from various DPU's via
the data highway and buffers the information on a hard disk for access
by the Application and Graphic processors. This system is integrated with the Facility Control System. It monitors
the voltage of 1,500 groups of four cells and the temperature of 72
individual cells in order to: - Determine the overall capacity of the battery - Diagnose the "health"
of the battery by singling out groups of cells showing low voltage.
The OPTO 22 system consists of 8 control system DPU's connected via
RS422/Fiber Optics to 72 enclosures containing 1, 500, + /- 1 0 volt
1/0 modules and Fiber Optic/RS422 communication devices. FIGURE 3 shows the overall PREPA Facility Control System configuration.
3.0 FCS CONTROL STRATEGY The FCS provides the supervisory control of two 10 MVA PCS'S. PCSL
A controls battery strings 1 - 3 and PCSLB controls battery strings
4 - 6. Each string consist of 1,000 cells connected in series. Strings
1, 2 and 3 are paralleled at the PCSL A DC switchgear bus. Strings 4,
5, and 6 are paralleled at the PCS1 B DC switchgear bus. The FCS controls
each PCS independently, but in parallel to one another. Since each PCS
is controlled independently, the operation of one PCS will not effect
the other PCS. 3.1 State of Charge Calculation Most of the control strategy in our application is based on amp-hours
and SOC percent calculation. The State of Charge (SOC) is the total
amount of energy stored (AMP-HOURS) in the batteries. The SOC calculation
is presented to the operator in AMP-HOURS (AH) and in PERCENT. The SOC
is currently being calculated for each string's DC current and per PCS's
main DC current. The operator can select to operate a PCS from one of
the three SOC calculations: -String SOC - Average SOC of individual strings -Main SOC - Calculated for the current across the main breaker. -Low SOC - Is the lowest string SOC for the associated PCS The FCS accumulates each string's individual current (AMPS) every
second, measured by current transducers at the feeder breakers, and
then divides this reading by 3600 to give AMP-HOURS. It also calculates
the percent SOC by taking the AMP-HOURS, and dividing this number by
the energy storage capacity of each string, currently defaulted at 2000
AMP-HOURS. A similar procedure is followed to calculate the SOC based
on the current flowing across the main DC breaker. 3.2. FCS/PCS Modes of Operation (see figure 4) Operational modes are achieved when the FCS places the PCS in the
RUN condition. Under these modes, the FCS will set the MW and MVAR demand
signals to the PCS to perform the required mode of operation. Each MW
& MVAR demand signal provided by the FCS have two 4-20 MA signals,
one signal is a positive demand, which represents power from the battery,
the other signal is a negative demand, which represents power to the
battery. A + 1 00 % demand represents 1 0 MW and -100 % demand represents
-10 MW. The various modes of operation are discussed below: 3.2.l. Normal Operation (MW Load Demand) The main function of the battery during normal operation is frequency
control. The FCS will perform a frequency control function to help regulate
the system frequency within a range of about +/- 0.2 HZ. There are two
curves for frequency control as depicted on figures F(x)4a and F (x)4b
of Figure 4-3. Both frequency curves are operator selectable. Each curve
has an associated deadband to avoid unnecessary cycling of the battery
and to allow the battery to share the load more equitably with frequency
control units. If the SOC is greater than 70 percent and the DC bus voltage is above
1950 volts(l.95 vpc), the FCS will high limit the MW load demand at
50 % ( 5 MW), allowing the batteries to supply power to the system(see
F(x)5b of Figure 4). Similarly, if the SOC is less than 70 percent and
the DC bus voltage drops below 1950 volts, the FCS will set the MW load
demand signal to 0 % (O MW), only allowing power to the batteries from
the system. The 2 KV DC and MW load demand limit function curves are
engineer adjustable. During normal operation, a 'trickle charge' is provided to the battery
to make up for charging losses. The FCS biases the selected MW negative
demand signal, from 0 to -50 amps ( 0 to -2.5 %), per connected string,
inversely proportional to the SOC, currently set at 70 % to 95 %. The
current and selected SOC function curves are engineer adjustable. (See
F(x)l, F(x)2 and F(x)3 of Figure 4-2). The operator at the central dispatch center may set the MW output
of the battery manually. The FCS will accept increase and decrease MW
reference signals from the Remote Terminal Unit (RTU) at the dispatcher's
location, in 25 % increments(5 MW, respectively, for each pulse received
from the RTU). The operator has the ability to override the RTU MW reference
signals and enter a MW demand signal (See Figure 4-1). 3.2.2 Normal Operation (MVAR Demand) During normal operation, the FCS performs a voltage regulating function
by controlling the flow of MVARS from the battery to the 1 1 5 KV bus
at the Sabana Liana Substation. The PCS accepts or supplies MVARS to
maintain the voltage within a narrow deadband, adjustable by an engineer.
The maximum MVAR capacity of the PCS is a function of the PCS MW's.
MW demand is the master signal and MVAR's are limited by the capacity
of the vector sum of MW and MVARS. The vector sum limit is equal to
+ /- 1 0 MVA for each PCS. (See F(x) 9 and F(x) 1 0 of Figure 4-5) 3.2.3 Maximum Discharge (Spinning Reserve) The FCS will place the PCS in Maximum Discharge mode during any incidents
of loss of generation, triggered by a low instantaneous frequency signal
or as selected by the operator. Three different trigger conditions have
been implemented. These are as follows:
The FCS will control the PCS at the constant power level and will initiate a 15 minute decreasing power ramp when one of the following conditions are satisfied: - Maximum discharge is on for the minimum allowable time, currently set for 60 seconds and system frequency is above 60.1 HZ for the minimum allowable time, currently set at 60 seconds. - Maximum discharge has been on for the maximum allowable time currently set at 15 minutes - Operator terminates maximum discharge. - The 2 KV DC bus voltage drops below the minimum voltage, currently
set at 1750 volts / 1.75 average volts per cell. At the end of the 15 minute decreasing power ramp, maximum discharge
will be reset and the FCS will be available to control frequency and
MVARS, provided the SOC is above 70 %. If the selected SOC is less than
70 % at the end of the 15 minute decreasing power ramp, the FCS will
set a flag, stating a refresh charge is required. 3.2.4 Charge Modes Charging of the battery may be initiated manually or automatically. Three charge modes are available: - Intermediate Charge - Refresh Charge - Equalize Charge The voltage set point for each charge mode is adjusted to correct for electrolyte temperature. a. Intermediate Charge Mode - As stated above, the operator can select the intermediate charge to initiate automatically or manually. If the charge selector is in automatic, the intermediate charge is initiated automatically if the following conditions exist: - PCS is not in maximum discharge. - Refresh charge is not required. - PCS is running. - Actual intermediate charge hour is equal to the hour set by the operator. - Selected SOC is less than or equal to 70%. Once the intermediate charge is initiated, the FCS will charge the
battery to the preferred SOC by a modified constant potential charge
method. The voltage set point for this charge is 2.28 volts per cell
on the average, adjusted for the average battery temperature, with a
current limit of 300 amps per connected string. The intermediate charge
is terminated automatically, when the accumulated SOC is above an operator
adjustable SOC value, currently set at 90 % SOC. b. Refresh Charge Mode - As stated above, the operator can select the refresh charge to initiate automatically or manually. Every maximum discharge cycle must be followed by a refresh charge if the selected SOC % is less than 70 %. If the charge selector is in automatic, the refresh charge is initiated automatically if the following conditions exist: - PCS is not in maximum discharge. - Refresh charge is required due to maximum discharge, or an operator adjustable number of days have elapsed since the last refresh charge. - PCS is running. - Actual refresh charge hour is equal to the hour set by the operator. - Selected SOC is less than 70% Once the refresh charge is initiated, the FCS will charge the battery
to the preferred SOC by a modified constant potential charge method.
The voltage set point for this charge is 2.38 volts per cell on the
average, adjusted by the average battery temperature, with a current
limit of 300 amps per connected string. The FCS determines the current
set point by taking 300 amps multiplied by the number of strings connected.
The refresh charge will terminate automatically, when the lowest strings
accumulated SOC is above an operator adjustable SOC value, currently
set at 104 % SOC and the 2 KV DC voltage has reached set point for an
operator adjustable period of time. Upon termination of the refresh
charge mode, the FCS will reset the connected strings and 2 KVDC SOC
accumulators to 100 % SOC. c. Equalization Charge Mode - The operator cannot select the equalization
charge to initiate automatically. It can only be executed manually.
This is done by measuring the average strings VPC at the tail end of
a refresh charge and comparing to the 1,500 OPTO 22 voltage values.
If more than 5 cell groups are in alarm due to a deviation of more that
200 mV per group (50 mV per cell), the control system will display a
message indicating that an equalization charge is required. Once the equalize charge is initiated, the FCS will charge the battery
to the preferred SOC by a modified constant potential charge method.
The voltage set point for this charge is 2.38 volts per cell on the
average, adjusted by the average battery temperature,with a current
limit of 300 amps per connected string. The FCS determines the current
set point by taking 300 amps multiplied by the number of strings connected.
The equalize charge will terminate automatically, when the selected
SOC is above an operator adjustable SOC value, currently set at 1 10
% SOC. Upon termination of the equalization charge mode, the FCS will
reset the connected strings and 2KVDC SOC accumulators to 100 % SOC. 3.3 FCS Miscellaneous System Operations The FCS also controls miscellaneous loops throughout the plant. The following is a general description of these loops. 3.3.1 Instrument Air System The FCS is controls the start / stop sequence for the Battery Air
Lift (Bubbling) Cycle. The bubbling cycle can be initiated automatically
or manually by the operator. The automatic sequence will operate a solenoid
valve, which will allow instrument air to mix the acid in each battery.
The bubbling cycle will run continuously for 15 minutes, every six hours.
All times are operator adjustable. 3.3.2 Battery Watering Cycle The FCS is controls the start / stop sequence for the Battery Watering
Cycle. The watering cycle can be initiated automatically, semi-automatically
or manually by the operator. The automatic sequence will operate 18
solenoid valves, which will allow water to fill 176 cells per solenoid
valve. The watering cycle will run continuously, cycling the 18 solenoid
valves for 4 minutes each, every 30 days. All times are operator adjustable.
The semi-automatic sequence will operate 18 solenoid valves, which
will allow water to fill 176 cells, per solenoid valve. The watering
cycle will run once, cycling the 18 solenoid valves for 4 minutes each. The manual sequence will allow the operator to select which solenoid
valve will open to allow water to fill 176 cells. The solenoid valve
will remain open for 4 minutes and will shut automatically. 3.3.3 HVAC and Fire Protection System The FCS monitors inputs from the fire protection system. If fire is
detected in either battery room , the FCS will issue a close command
to the fire dampers. The operator will not be able to open the fire
dampers until the fire detection alarm is cleared. If fire is detected in the inverter room, the FCS will issue a close
command to the fire dampers for the inverter room. The operator will
not be able to open the fire dampers until the fire detection alarm
is cleared. If fire is detected in the inverter / control room, the
FCS will shutdown the HVAC system. 3.3.4 Battery Ventilation Fans The FCS controls the start/ stop and high/low speed sequences for
the Battery Ventilation Fans. There are a total of six ventilation fans,
three per battery room. The fans normally run at low speed until the FCS issues a start high
speed command due one of the following conditions: - two or more battery room temperature monitors are 5 DEGF greater
than ambient air temperature. - one of the four battery room hydrogen monitors are greater than
30% - average battery cell temperature is greater than 120 DEGF. 3.3.5 Bess Efficiency Calculations The Total Bess Efficiency and the Battery Efficiency accumulators
are calculated for each operating cycle, except for Equalize charge.
The accumulators start with the battery at 100 % SOC and end with the
completion of any refresh charge. The PCS Input Efficiency and the PCS Output Efficiency accumulators are calculated over each operating cycle, except for equalize charge. The accumulators start with the battery at 100 % SOC and end with the completion of any refresh charge. These efficiencies are also calculated using instantaneous values. All the efficiency calculations are displayed to the
operator / engineer. The FCS calculates the following efficiencies as
required: - Total BESS Efficiency- Divide the accumulated AC KWH Output to the system by the accumulated AC KWH input to the BESS. - PCS Input Efficiency- Divide the accumulated DC KWH output from the PCS to the battery by the accumulated AC KWH input to the PCS from the system. - PCS Output Efficiency- Divide the accumulated AC KWH output from the PCS to the system by the accumulated DC KWH input to the PCS from the battery. - Battery Eff iciency- Divide the accumulated DC KWH
output from the battery by the accumulated DC KWH input to the battery. 4.0 EXPERIENCES DURING FCS IMPLEMENTATION In the early stages of implementation, the FCS Configuration Functional
Specification was extremely simplified (approximately 50 % of the final
Functional Specification). The main reason for the growth in the functional
specification can be attributed to the lack of design, application and
controls experience required to control the Battery Energy Storage System.
As the project developed and implementation began, there were many questions
raised on how to properly control the BESS. Through a concentrated team
effort, all the questions were answered and the revised control philosophy
developed. During the six week factory staging, the BESS control philosophy
was subjected to extensive testing. As a result of these tests and subsequent
lessons learned throughout the first few months of operation, various
schemes of the control philosophy were changed and revised to develop
the final BESS control philosophy described in this paper. 4.1 Converter Related Problems The Battery Plant at Sabana Llana has been fully operational since
November of 1994. Prior to that date, the Plant operated on a limited
fashion from June 1994 to October 1994 due to frequent trips caused
by several problems on both converter units. These problems affected
the implementation of the control system. The causes ranged from defective
electronic cards at all the PCM modules, to faulty firmware logic at
the Distributed Micro Controller (DMC), to several GTO failures. Several
modifications to the hardware and firmware were required to correct
most of these problems. 4.2 Lessons Learned With the experience gained through the first months of operation,
several control philosophy schemes were modified to meet plant operation
requirements. Among them are the following: 1 . Limits for charging and discharging the cells during frequency
regulation, based on SOC and DC voltage, were included in the control
logic as a protection against over discharging the cells. 2. Macros for additional frequency regulation curves were added in
order to suit different system requirements and to allow the battery
to share the control load more efficiently with the rest of the available
power generation. 3. The cell charge logic was modified to improve the charge termination
scheme. Timers and logic gates were incorporated to accomplish this. 4. Logic was added to prevent battery overcharge and incorrect calculation
of SOC during frequency regulation. To achieve this, charge load is
ramped down as the SOC approaches 95 percent and is totally disabled
at 100 percent. 5. Incorporated small dead bands for the current integration due to
current transducers inaccuracies around zero amperes. 6. Modified wiring Of the under frequency relay to improve the rapid
discharge response time. The relay contact for rapid discharge goes
now directly to the converter units instead of to the FCS. The control
is then released from the converters to the FCS, three seconds after
the rapid discharge has been executed. 7. Modified the logic for the determination of the equalizing charge
necessity. 8. Added logic to make more flexible the implementation of programmed
charge modes. 9. Other miscellaneous control logic and graphic additions and modifications
were incorporated to make the system more user friendly and flexible. 5.0 CONCLUSION The Facility Control System (FCS) provides supervisory control of
all BESS functions. It allows operators to monitor, control and tune
all the facility processes. The FCS is the main interface between the
battery and the power conditioning system (PCS). By interfacing with
the PCS microcontroller, the FCS sets operational modes to include battery
discharge for frequency control and instantaneous reserve; battery charging,
voltage control, as well as start-up and shut-down. Other critical processes
provide for battery maintenance, such as electrolyte agitation, and
watering of cells; and safety (fire protection and hydrogen concentration
alarms). The implementation of control systems for utility battery storage
plants is an unusual application. Therefore it requires extensive teamwork
and cooperation between the facility designers, suppliers of the main
components, utility personnel and control system integrators. |