INSTALLATION DESCRIPTION BRIEF

INDUSTRY: IPP (Independent Power Producer)

APPLICATION: 560 MW Combined Cycle Generation Plant

COMMERCIAL OPERATION:  May 2000

UCH POWER LIMITED – A TENASKA COMPANY

UCH POWER PROJECT

Dera Murad Jamali, Balochistan, Pakistan

OPERATOR:  E.S.B. INTERNATIONAL

EPC CONTRACTOR: RAYTHEON - EBASCO OVERSEAS LIMITED

DESCRIPTION:

560 MW Low BTU Gas/Distillate Fired, Combined Cycle Generation plant consisting of three gas turbine generators exhausting into three-three pressure Heat Recovery Steam Generators, (HRSGs) supplying steam to a single condensing steam turbine generator. 

Plant consists of the following systems that are controlled via the Distributed Control System.

  • (3) Gas Turbine/Generators (GE – Frame 9E) – Limited Control
  • Steam Turbine/Generator (General Electric) – Limited Control
  • (3) Heat Recovery Steam Generators (Vogt)
  • Demineralizer System (Glegg)
  • Auxiliary Boiler
  • Circ. Water and 12-cell Cooling Tower
  • Electrical System

All Balance of Plant Systems - Condensate, Feedwater, Fuels, Mechanical Auxiliaries, etc.

CONTROL EQUIPMENT:

Leeds+Northrup MAX 1000 DCS with the following components:

  • (3) WorkStations including:
  • (2) Real-Time Processors
  • (5) Graphics Processors (OPS)
  • (2) Applications Processors (EWS)
  • (5) Non-redundant Distributed Processing Units (DPU)
  • (11) Redundant Distributed Processing Units (DPU) Pairs
  • (7) Remote cabinets to handle specific areas of the plant.
  • 2794 Total I/O Supplied:  438 AI  168 AO  952 DI  645 DO  165 TC  42 RTD  128 PI  256 SOE

SPECIAL FEATURES:

  • (4) GE Speedtronics Mark 5 - Modbus Communications Links
  • (2) Allen Bradley Data links to the Water Treatment Plant and Demin System
  • OPTO 22 Data-link to remote I/O location for Raw Water Pumps
  • Multiplexed Color Copier